How to install steel platform

Share on facebook
Share on linkedin
Share on skype
Share on email

What is steel platform ?

The steel platform just like a sandwich that made of H steel materials,it’s main frame is assembled with H steel.So,it’s often be called h steel mezzanine.

In the previous article, we have already talked about its advantages,when is it necessary to purchase it,what should be known before purchasing,and so on.In this article, we will discuss how to install steel platform.

I-beams (H-shaped steel /I-beam) are widely used in fields such as building construction, factories, Bridges, equipment platforms, and steel structure floor beams due to their strong bending resistance, high section efficiency, and convenient construction. The correct installation of I-beams is directly related to structural safety and service life. The following systematically introduces the full process precautions for the installation of I-beams.

Preparations before installation steel platform :

Layout steel platform according to the drawings placed in the order:

Carefully check the steel platform structural construction drawings and the detailed steel structure drawings to ensure that the node forms (bolted, welded, fully bolted, and mixed bolted and welded) are consistent with the drawings.

Re-inspection of materials upon arrival for the steel platform

According to the provided list of steel platform, check if the quantity is correct.

On-site condition confirmation for the steel platform to install

The installation site is consistent with the sketch? Is the ground flat? Can water, electricity and lighting be used normally? Has the obstacle been cleared? Has the fire escape been left open?Is the auxiliary equipment installed in place? Forklift must be provided for installation.

Technical preparations before hoisting for the steel platform

Determine the hoisting plan for the steel platform

For 10 to 20-ton truck cranes or crawler cranes, the lifting points are generally set at 1/5 to 1/4 of the beam length to prevent local instability of the web

For large-span and heavy I-beams (>50kg/m), double cranes are required for lifting or balance beams should be used.

Please look at the installation picture.

steel platform
steel platform

temporary support for the steel platform

Temporary stirrups (made of channel steel or Angle steel) should be set up every 4 to 6 meters to prevent lateral instability of the beam.

When the span is greater than 12m or the beam height is greater than 800mm, temporary supports must be set up.

Preparation of connecting plates, bolts and welding materials for the steel platform

The high-strength bolts are ready

Installers must wear safety helmets

The installation process flow of the steel platform

1. surveying and setting out

Use a total station or a laser plumb Bob to measure the column axis and corbel elevation to the top of the column.

steel platform
steel platform

Mark the center line and edge line of the beam on the corbels (with red paint or a marker pen)

2. Place the columns according to the positioning,Put the two H columns in a fixed place.

steel platform
steel platform

3.Place the crossbeam.

steel platform
steel platform

First, hoist the main beam, place it above the two columns, and align the holes properly . Lock it with screw and nut.

Lift the secondary beam again to form a stable frame for the entire structure.Where there are holes, lock them respectively with screws and nuts. Please note that the screw and nut do not need to be tightened too much in the early stag in order to adjust. Initial twist → re-twist → final twist.

4.Calibration and permanent fixation.

After installation, check if there are any omissions where the screw nuts are not locked

5.Check if the site is leaking. If the factory building is leaking, please pay attention to repairing the house to avoid the materials being corroded by rainwater and affecting it’s service life for the steel platform.

steel platform
steel platform

6.Steel plates should be laid after the overall framework is built.After the steel plates are placed, they should be stabilized with self-tapping screws.

7.The final step is to install the guardrail, stairs,lift.

steel platform
steel platform

8.No matter what, safety comes first. Please be careful during the installation process.As I-beams are relatively heavy, it is recommended that they be installed by professionals

steel platform
steel platform

By mastering the above key points, the installation of I-beams can be achieved as “safe, fast, aesthetically pleasing and economical”. In actual operation, flexible adjustments should also be made in combination with the design requirements of specific projects

The applicable scenarios for the h steel mezzanine:
1.Warehousing and logistics: Construct a loft-style shelving platform and high-level shelves to maximize storage space.

2.Industrial factory buildings: As the load-bearing structure and equipment platform, they provide a stable working space.

3.Floor construction: The floor structure used in multi-story buildings.

4.Mechanical manufacturing: Used for manufacturing various machine bases or frameworks.

The I-beam steel platform, due to its excellent comprehensive performance, is a commonly used solution in modern industrial and commercial buildings.

Finally, we sincerely invite you to visit our factory at any time.

Feel free to contact me if you want to buy Finally, we sincerely invite you to visit our factory at any time.

Feel free to contact me if you want to buy h steel mezzanine
Whatsapp : 18824537792
E-mail : [email protected]

Share on facebook
Share on linkedin
Share on email
Share on skype

Leave a Reply

Your email address will not be published. Required fields are marked *

ten + fifteen =

Related Products

back to top
WhatsApp

Get an instant quote from our most experienced consultants.